Short description
The Port of Frederikshavn is planning to build a new oil terminal and put out the work for tender in a turn key contract including design, construction and commissioning. It is expected that the work will commerce in the first quarter of 2019 and that the finished oil terminal must be ready for use in the fourth quarter of 2020.
The overall plant must as a minimum comprise:
— tank farm with 11 tanks and a total capacity of 74 400 m
— 2 berth loading facilities at the quay,
— 1 truck loading facility,
— piping systems including pumps and pumping room,
— central heating system for heating of some of the tanks,
— vapour return system with filter,
— drain systems,
— electrical installations and SCADA system,
— personnel facilities,
— workshop,
— 2 guardhouses or similar,
— storage areas for EMSA equipment,
— fences and gates.