It is required surveying services/services from a mark-out engineer/surveyor in connection with the development of the new double track Arna-Bergen The projects paramount objective is to prepare for increased capacity for train conveying at the section Arna-Bergen and this includes upgrading of Arna Station and a new tunnel through Ulriken. The length of the tunnel is 7,8 km with transverse passages, technical rooms and crossing tracks. The main works will be executed at the facility in Arna.
Assignments:
— Inspection of quantities and surveyor's certificate of area measure issued by the contractor in connection with Progress.
— Control of limits of tolerance.
— Random controls of e. excluding limits of tolerance, navigation, drilling holes and equivalent times.
— Measuring-in existing tracks and physical objects.
— Other relevant assignments.
Section V: Award of contract
Contract No: 1
Lot No: 1 - Lot title: Purchase of surveying services and services from a mark-out engineer/surveyor for the project new double track Arna-Bergen
V.1) Date of contract award decision:
13.2.2015
V.2) Information about offers
V.3) Name and address of economic operator in favour of whom the contract award decision has been taken
E-mail: 974679442Exact Geo Survey AS, Østre Aker vei 24, 0581 Oslo, NORWAY, bjarte.nedkvitne@teamexact.com