The works include blasting of a 680 m tunnel with a cross-section of 14 m2. The laying of 300 m culvert with a diameter of Ø2,400 (Ø2,500) and a 25 m culvert with a diameter of Ø2,000. The construction of a stormwater with sand traps, a staircase in the crossing between the culvert and the tunnel (Alberthaugen) and the construction of a wall with access in the crossing between the tunnel and the culvert (Rishaugen
A temporary road for construction purposes and an area for temporary, pre-fabricated cabins shall be established, as well as reinforce the existing road through Nordland Art Centre. The Stormyrveien road shall also be upgraded and a new Parking area in connection with the staircase shall be constructed.