Dato for innlevering er passert
Energinet.dk, owner of the Vester Hassing synchronous condenser (VHA G1), has decided to invite tenders for major overhaul of the ASEA salient pole generator (phase shifter). VHA G1 is an 80MVA outdoor synchronous condenser unit commissioned around 1965 and it is still in operation. The stator winding (12kV) was rewound in 1982. The overhaul is planned to start week 39, 2017 ending no later than week 51, 2017. The major overhaul (which includes withdrawal of the rotor and bringing it to workshop), takes place at the Vester Hassing high voltage substation, Energinet.dk, Elsamvej 73, DK-9310 Vodskov.