Eesmärk
In January 2009 the Danish Parliament decided to fund a 18 000 000 000 DKK national replacement programme of renewing all Danish railway signaling by 2023 (ERTMS). As part of this, in 2009, Banedanmark entered a main consultancy agreement concerning technical consultancy and support (multiconsultancy services) with a Joint Venture (see Section V.2.3). This initial contract was subject to a call for competition. In the contract notice from 2009 it was stated that the estimated value of the contract was between 500 000 000 DKK and 1 000 000 000 DKK, and that the stated amount was a rough estimate. During 2018 – 2019, the programme has been subject to re-planning, and the final roll-out has been postponed to 2030 due to an unforeseen complexity in the installation of the IT based signaling programme. This notice regards the concluded amendment of provisions to the contract following the re-planning of the signaling programme.