Assignment text
Laying of approximately 10 km long 132 kV 3-core XLPE insulated submarine cable part of a new 132 kV cable system HK13018 AMV-SMK to be installed between Svanemøllebugten and Amager Power Plant inside and close to the Port of the City of Copenhagen. The weight of the cable to be laid is approximately 700-800 ton. Removal of 4 km submarine part of decommissioned 132 kV LPOF 3-core cable system HK1234 AMV-SMK installed in the Port of the City of Copenhagen between Fortkaj in the inner part of the port and Amager Power Plant. The weight of the cable to be removed is approximately 160-170 ton. The cable laying and removal of cable is scheduled for execution in immediate extension of each other foreseen to be handled in Q4, 2021 and or in Q1, 2022.