Kriegers Flak Combined Grid Solution (KF CGS) 150 kV 3 core submarine cable including transport, laying and installation.

Information

Udbud med forhandling
30-12-2016 09:14 (GMT+01:00)

Indkøber

Energinet.dk Energinet.dk
Eva Damsted Juhler Eva Damsted Juhler
Tonne Kjærsvej 65
7000 Fredericia
Danmark
28980671

Tildelingsinformationer

Section V: Award of contract
Contract No: 1
Lot No: 1
Title
Kriegers Flak Combined Grid Solution (KF CGS) 150 kV 3 core Submarine cable including Transport and laying
A contract/lot is awarded: yes
V.2.1) Date of conclusion of the contract: 2016-12-15
V.2.3) Name and address of the contractor:
Agree to publish?: yes
The contract has been awarded to a group of economic operators: no
NKT Cables A/s
DK25711548
Toftegaardsvej 25
4550 Asnaes
Denmark
Telephone: +45 59661061
E-mail: nicolaj.bjerregaard@nktcables.com
Fax: +45 59661215
NUTS code: DK
Internet address: http://www.nktcables.com
The contractor is an SME: no

Mercell A/S

En del af Mercell, en af Europas ledende aktører inden for formidling af information mellem indkøber og leverandør på det professionelle marked. CVR nr. 25698851

Kontakt

Klik her for at gå til support

+45 63 13 37 00
Mercell A/S | B!NGS