The tender is for one Biogas Plant, producing biogas from animal manure and other biowaste with a mass distribution of 75 % to 25 % respectively. The produced biogas is to be upgraded to natural gasquality in a separate Biogas Upgrading Plant (not part of this tender) and distributed in the Danish natural gasgrid.
The contract type will be “turn key” including weighing in and receiving station for feedstock.
To delivery of the produced biogas to the upgrading plant and facilities for delivery of residual products to trucks for further use or disposal. The contract will cover civil, mechanical and electrical and any other relevant work, from engineering to commissioning of the complete plant.
Section V: Award of contract
V.1.1) Date of contract award decision:
31.1.2014
V.1.2) Information about offers
Number of offers received: 4
V.1.3) Name and address of economic operator in favour of whom the contract award decision has been taken