The existing 132 kV GIS plant at Avedøreværket (Avedøre Power Plant) abbreviated “AVV” will be replaced during the summer of 2018. This change requires replacement of the existing Cable Terminations as they do not fit into the new GE F35 145 kV GIS. Therefore delivery and installation of new Cable Terminations is required.