In connection with a planned upgrade and increase of capacity in the plant for storm water treatment — henceforth referred to as RVR, there will be a need for New process facilities for conveying and treatment of screenings. The planned increase of capacity for the storm water plant will be from present level of 3,5m3/s to 8,0m3/s. This implies an extension of the present facilities by more channels and screens. Screenings separated from RVR and transported by means of conveyors to a separated plant for washing and further conveying to containers. The scope of this contract is the supply and installation as follows:
— Band screens,
— Conveyors,
— Channel pen-stocks.
Contract work duration is set to 8 and 1/2 months. Planned commissioning of RVR is summer of 2017.