Avinor AS is planning a rebuild of the arrival area - International at Stavanger airport Sola. Due to necessary rearrangements, a new baggage handling system for arriving luggage shall be procured and installed. The system will include a new revolving roundabout with conveyor including fire and security locks.
The Delivery shall include the following provisions:
1. Dismantle and removal of existing baggage arrangement and control system.
2. Delivery and installation of the complete new system for arriving baggage.
3. OPTIONAL: Future relocation and rebuilding of the delivered system.
The initial study has stipulated the total Contract value to approximately 4,5 MNOK ex VAT whereas this includes the optional delivery to approx. 1 MNOK.
Time of Delivery:
a) External baggage arrangement outside terminal shall be finished by 30.5.2014
b) Working time frame for baggage arrangement inside terminal included completion of total installation is from June 2nd to 13.6.2014.