Mortensrud — Joint infrastructure is an infrastructure project located at Mortensrud as a general contract described according to SVV’s (Norwegian Public Roads Administration’s) process codes.
Technical infrastructure:
— ditch works for 11 kV HS pipes (four to eight units), length approx. 710 m;
— ditch works for for FV pipes DN500, including connections in lesser dimensions, length approx. 900 m;
— ditch works for FV pipes DN200, length approx. 275 m;
— new water pipes DN400, length approx. 470 m;
— new storm water pipes, length approx. 180 m;
— drawing of storm water pipes Ø280, length approx. 370 m;
— surface water system for roads, including two diversion magazines, length approx. 1 000 m;
— lighting system for roads, length approx. 1,650 m.
Establishing/upgrading of roads:
— Lofsrudveien, normal width 16.2 m, length approx. 1 020 m;
— Upgrading of side roads and crossings;
— Klemetsrudveien, normal width 9.5 m, length approx. 300 m;
— access road to Lofsrud farm, width 4.75-7.25 m length approx. 300 m.