Assignment text
Fingrid conducted a public procurement during the fall of 2020 asking Tenders for the delivery of two (2) 400/400/125 MVA and 410/120/21 kV power transformers for Pysäysperä substation (Main Delivery). In addition, eight (8) pieces of 400/400/125 MVA and 410/120/21 kV power transformers were asked as an option (Optional Delivery). The delivery of power transformers, including all needed transportation and erections, was to be performed as turnkey deliveries. The final tenders were given in December 2020 and the procurement decision was made in the beginning of 2021.